Figure shoreline and slope quantities from the required armor layer depth, since this stone is installed deeper than ordinary landscape rock.

Enter your project dimensions

ft
Enter a length greater than 0
ft
Enter a width greater than 0
ft
Enter a diameter greater than 0
in
Enter a depth between 0.25 and 24 inches

A ton of riprap covers roughly 17 square feet. That figure is correct. Because armor rock is installed in layers of 12 inches or more, each ton covers about a tenth as much area as landscape stone, and the needed pile can seem surprisingly small before it is spread across the bank. This calculator uses layer thickness and 3,100 lb per cubic yard for stone generally sized 4 to 12 inches and larger.

How to measure an armor bank

  1. Use the distance along the slope face rather than the level ground, then multiply it by the bank or channel length.
  2. Plan on a layer 1.5 to 2 times the size of the largest stone. For meaningful erosion protection, use 12 inches as the minimum working depth.
  3. Divide cubic feet by 27 for cubic yards, then multiply by 1.55 for tons.
Tons = (Slope-face area sq ft × Layer thickness in ÷ 12) ÷ 27 × 1.55

Ton coverage

Layer thickness1 ton coversTons per 100 sq ft
12 inches≈ 17 sq ft5.7
18 inches≈ 12 sq ft8.6
24 inches≈ 9 sq ft11.5

Steps for keeping riprap in place

  • Start with a base layer: place non-woven geotextile beneath the rock, or use 3-4 inches of #4 stone. On bare soil, riprap can appear stable for a season before erosion beneath the bank causes it to settle.
  • Build the toe into the bank. Place the lowest row below the waterline or expected scour depth, as undermining usually starts from below.
  • Shape the bank to 2:1 or flatter before setting the stone. Slopes steeper than that call for engineering, not just extra material.
  • Use equipment or hand placement on the exposed upper course, fitting stones together so they lock in place instead of stopping where they fall.
  • Extend an outlet apron 4-6 pipe diameters downstream from culverts. This is the section where flowing water cuts into the ground.

Example: 50 feet of pond bank

Along 50 feet of shoreline, a 6-foot bank face equals 300 square feet. For an 18-inch-thick layer, calculate 300 x 1.5 = 450 cubic feet, or 16.7 cubic yards. That works out to about 26 tons of riprap, or 27 including a small extra amount. Use a roll of geotextile beneath it, or bed the stone on about 4 tons of #4 stone instead. Check the truck access before you place an order, especially the final 20 feet near the pond, where a loaded truck can sink. Relocating stone costs twice as much when it has to be moved twice.

Following the first major storm

After water levels recede, make a pass along the bank. Note any rock displaced near the toe, exposed earth in the stone, visible fabric, or erosion around the outfall apron. Put shifted pieces back in place and use reserve stone to fill sparse areas. A brief check twice yearly, especially after freeze-thaw weather, keeps the armored slope in order.

A brief guide to stone sizes

Choose riprap according to water force. Four-to-eight-inch material works for pond banks, slow streams, and downspout outfalls. Eight-to-twelve-inch rock fits lake edges affected by boat wake and quicker channels. Highway and spillway work has specified stone classes and depths, so use the project drawing rather than this page. If two sizes are under consideration, select the larger material and increase layer thickness. More weight provides greater tolerance.

Riprap amounts, sizing and installation

How can I estimate the rip rap needed?
Take the slope-face area, multiply it by layer depth in feet, divide by 27, then multiply by 1.55. For a 10 x 10 sample area at 12 inches, the result is 37 cubic feet, or about 2.1 tons.
What area will 1 ton of riprap cover?
At a 12-inch depth, plan on about 17 square feet; at 18 inches, about 12. For budgeting at the usual layer depth, allow 5.5 to 6 tons for each 100 square feet.
What is the size of a 1 ton rip rap pile?
A ton makes a pile of about two-thirds of a cubic yard, near the volume of a washing machine, containing 25-35 stones at the 6-8 inch size. It may look modest in a pile, but at proper depth it covers a 4 x 4 bank area.
What is the cost of 1 ton of rip rap?
RipRap costs more than construction stone and is priced by size class. See the live amount on our RipRap product page; delivery is free. Fabric and bedding stone add a fraction more, and getting those base materials right matters to the installation.
What depth should a rip rap layer have?
Use a layer one and a half to two times the largest stone dimension, with 12 inches as the minimum. Standard 4-12 inch residential material generally takes 12-18 inches. Larger rock or faster water can require 24.
Is hand placement possible for rip rap?
Hand placement can work for stone up to about 6-8 inch when using gloves and proper lifting: one ton involves 25-35 lifts. Larger rock calls for machinery. A skid steer can place in an hour what hand installation takes a day.